Drilling and blasting
 (

Drilling and blasting is the controlled use of and other methods, such as gas pressure blasting pyrotechnics, to break rock for excavation. It is practiced most often in , and civil engineering such as , tunnel or road construction. The result of rock blasting is often known as a rock cut.

Drilling and blasting currently utilizes many different varieties of explosives with different compositions and performance properties. Higher explosives are used for relatively hard rock in order to shatter and break the rock, while low velocity explosives are used in soft rocks to generate more gas pressure and a greater heaving effect. For instance, an early 20th-century blasting manual compared the effects of black powder to that of a wedge, and dynamite to that of a hammer. The most commonly used explosives in mining today are based blends due to lower cost than .

Before the advent of tunnel boring machines (TBMs), drilling and blasting was the only economical way of excavating long through hard rock, where digging is not possible. Even today, the method is still used in the construction of tunnels, such as in the construction of the Lötschberg Base Tunnel. The decision whether to construct a tunnel using a TBM or using a drill and blast method includes a number of factors. Tunnel length is a key issue that needs to be addressed because large TBMs for a rock tunnel have a high capital cost, but because they are usually quicker than a drill and blast tunnel the price per metre of tunnel is lower.

(2025). 9783540251965, Springer-Verlag. .
This means that shorter tunnels tend to be less economical to construct with a TBM and are therefore usually constructed by drill and blast. Managing ground conditions can also have a significant effect on the choice with different methods suited to different hazards in the ground.


History
The use of explosives in mining goes back to the year 1627,Gary L. Buffington, The Art of Blasting on Construction and Surface Mining Sites , American Society of Safety Engineers (2000). when was first used in place of mechanical tools in the (now ) town of Banská Štiavnica. The innovation spread quickly throughout Europe and the Americas.

The standard method for blasting rocks was to drill a hole to a considerable depth and deposit a charge of gunpowder at the further end of the hole and then fill the remainder of the hole with clay or some other soft mineral substance, well rammed, to make it as tight as possible. A wire laid in the hole during this process was then removed and replaced with a train of gunpowder. This train was ignited by a , often consisting simply of brown paper smeared with grease, intended to burn long enough to allow the person who fires it enough time to reach a place of safety.

The uncertainty of this method led to many accidents and various measures were introduced to improve safety for those involved. One was replacing the iron wire, by which the passage for the gunpowder is formed, with one of copper, to eliminate that could ignite the powder prematurely. Another was the use of a . This consisted of small train of gunpowder inserted in a water-proof cord, which burns at a steady and uniform rate. This in turn was later replaced by a long piece of wire that was used to deliver an electric charge to ignite the explosive. The first to use this method for underwater blasting was who employed it in 1839 to break up the wreck of the British warship HMS Royal George which had become a shipping hazard at . The National Cyclopaedia of Useful Knowledge, Vol III, (1847) London, Charles Knight, p.414.

An early major use of blasting to remove rock occurred in 1843 when the British civil engineer used 18,000 lbs of gunpowder to remove a 400-foot-high chalk cliff near as part of the construction of the South Eastern Railway. About 400,000 cubic yards of chalk was displaced in an exercise that it was estimated saved the company six months time and £7,000 in expense.

While drilling and blasting saw limited use in pre-industrial times using (such as with the Blue Ridge Tunnel in the United States, built in the 1850s), it was not until more powerful (and safer) , such as (patented 1867), as well as powered were developed, that its potential was fully realised.

Drilling and blasting was successfully used to construct tunnels throughout the world, notably the Fréjus Rail Tunnel, the Gotthard Rail Tunnel, the , the and even the longest road tunnel in the world, Lærdalstunnelen, are constructed using this method.

In 1990, 2.1 billion kg of commercial explosives were consumed in the United States (12 m3 per capita), representing an estimated expenditure of 3.5 to 4 billion 1993 dollars on blasting. In this year the Soviet Union was the leader in total volume with 2.7 billion kg of explosives consumed (13 m3 per capita), and Australia had the highest per capita explosives consumption that year with 45 m3 per capita.

(1994). 084938978X, CRC Press. 084938978X


Procedure
As the name suggests, drilling and blasting works as follows:

  • A blast pattern is created
  • A number of holes are drilled into the rock, which are then partially filled with explosives.
  • Stemming, inert material, is packed into the holes to direct the explosive force into the surrounding rock. Chapter 7, Loading Boreholes , National Park Service Handbook for the Transportation, and Use of Explosives , 1999, last updated 2007; page 110.
  • Detonating the explosive causes the rock to collapse.
  • Rubble is removed and the new tunnel surface is reinforced.
  • Repeating these steps until desired excavation is complete.

The positions and depths of the holes (and the amount of explosive each hole receives) are determined by a carefully constructed pattern, which, together with the correct timing of the individual explosions, will guarantee that the tunnel will have an approximately circular cross-section.

During operation, may be used to contain the blast, suppress dust and noise, for fly rock prevention and sometimes to direct the blast.

(2025). 9780203626450, . .


Rock support
As a tunnel or excavation progresses the roof and side walls need to be supported to stop the rock falling into the excavation. The philosophy and methods for rock support vary widely but typical rock support systems can include:
  • or rock dowels
  • Ribs or mining arches and lagging
  • Cable bolts
  • In-situ concrete
Typically a rock support system would include a number of these support methods, each intended to undertake a specific role in the rock support such as the combination of rock bolting and shotcrete.


Gallery
Image:Blast_hole_drilling.jpg|Blast hole drilling with Tamrock Scout 700 File:Bingham Canyon Mine, west face detail, Utah.jpg|Blast-hole drilling at the Bingham Canyon Mine, Utah. Note the pattern of drill holes being prepared for blasting. Image:Charging_with_anfo.jpg|Loading blast holes with Image:P1010759.JPG|Rock surface newly blasted. This is called pre-split, it's a technique to leave a smooth face. Image:Sideling_hill_road_cut.jpg| road cut formed by rock blasting File:Rixö granitbrott 7.jpg|Tire blasting mats for fly rock prevention and dust suppression. File:Blast notice.png|Map describing the clearance zones during blasting in a limestone quarry. These notices are produced by surveyors (see ). File:Prospect Quarry.jpg|Blast hole drilling in a quarry at Prospect Hill, , Australia


See also
  • Building implosion
  • International Society for Explosive Engineers


External links
  • "Air Curtain Fences Blast" Popular Mechanics, August 1954, pp. 96–97, the delicate controlled blast in 1954 to connect the two reservoirs at a Canadian Niagara Falls power station.
  • This is an extensive survey of techniques used in the early 20th century.

Page 1 of 1
1
Page 1 of 1
1

Account

Social:
Pages:  ..   .. 
Items:  .. 

Navigation

General: Atom Feed Atom Feed  .. 
Help:  ..   .. 
Category:  ..   .. 
Media:  ..   .. 
Posts:  ..   ..   .. 

Statistics

Page:  .. 
Summary:  .. 
1 Tags
10/10 Page Rank
5 Page Refs
1s Time